What Is a Site Inspection? Meaning, Types and Stages

What a site inspection is, who carries one out in Ireland, what is checked at each stage of a build, and what happens when the work falls short.

A site inspection is a planned visit to a building site by a competent person to check the work, or the site itself, against a standard: the design drawings, the Building Regulations, or health and safety law. It is recorded in writing, and anything that falls short is noted, put right and checked again.

That is the meaning in one paragraph. In practice, on an Irish job, the phrase covers several different visits made by different people for different reasons, and most of the confusion on the phone comes from not knowing which one is being asked for.

What does a site inspection actually do?

It compares what has been built with what should have been built, at a moment when the difference can still be fixed cheaply. A foundation with the wrong reinforcement is a morning's work to correct before the concrete lorry arrives, and a structural problem for the life of the building afterwards.

It also leaves evidence. A building is mostly made of things nobody will see again: footings, rebar, radon membranes, drains, the fixings in a roof. The inspection record is the only proof those things were checked, and it is what a certificate, a solicitor or a lender relies on years later.

What an inspection is not is supervision. The Department's Code of Practice is explicit that the assigned certifier's role "does not include responsibility for the supervision of any builder", and that because not every item can be examined, the builder's own supervision is of critical importance. An inspector checks the work at chosen points; the builder is responsible for all of it.

Who carries out site inspections in Ireland?

Five kinds of inspection turn up on Irish sites. They answer to different rules and produce different records.

InspectionWho carries it outChecked againstWhat it produces
Engineer's inspectionThe designer of that element, often as ancillary certifierThe design drawings and calculationsInspection report, ancillary certificate
Assigned certifier's inspectionA registered architect, chartered engineer or registered building surveyor appointed by the ownerThe Building Regulations and the lodged designInspection plan as implemented, Certificate of Compliance on Completion
Building control inspectionAn authorised officer of the local building control authorityThe Building RegulationsInspection report, enforcement where needed
Health and safety inspectionThe contractor's competent persons, the PSCS, and HSA inspectorsThe Safety, Health and Welfare at Work Act 2005 and the Construction Regulations 2013Statutory forms, notices where needed
Existing building inspectionAn engineer, architect or surveyorThe regulations, the planning permission, or the condition of the buildingOpinion on Compliance, survey or snag list
OwnerAppoints all three before work starts
appoints
Design certifierCertifies the design at commencement
Assigned certifierPlans and coordinates the inspections, signs at completion
BuilderBuilds and supervises the work, signs at completion
coordinates
Designers as ancillary certifiersThe engineer, the architect and specialists inspect their own work and certify it
lodged on the BCMS
Building control authorityInspects a share of jobs by risk and at random, and can enforce
On a separate track: site safetyThe PSCS coordinates safety on site. HSA inspectors visit unannounced and can stop work.
Who answers to whom on a job inside BCAR, with site safety on a track of its own.

The engineer's inspections

Under the Code, each designer carries out the inspections pertinent to their own part of the design, as agreed with the assigned certifier, keeps records, and provides an ancillary certificate at the end. For the structure, that means the engineer who designed the foundations and frame comes to see them before they are covered.

The assigned certifier's inspections

Where the work is inside statutory certification under the Building Control (Amendment) Regulations (BCAR), the owner appoints an assigned certifier before work starts. The assigned certifier prepares the preliminary inspection plan lodged with the commencement notice, inspects and coordinates everybody else's inspections, collects the ancillary certificates, and signs the Certificate of Compliance on Completion with the builder. Design certifier and assigned certifier are two separate appointments, and the difference is worth knowing before you ask anyone to quote.

Building control authority inspections

The council does not approve your design. Its building control officers inspect a share of the projects notified on the Building Control Management System (BCMS), chosen by risk analysis and by random selection, and they have strong powers to inspect work in progress and enforce. A council inspection is a check on the system; it does not replace the owner's own.

Health and safety inspections

These are about the people on site rather than the building. The PSCS coordinates safety during construction, contractors' competent persons inspect excavations and scaffolds and record it on the HSA's statutory forms, and HSA inspectors visit sites unannounced. On the design side, the PSDP coordinates the designers so the building can be built and maintained safely, but the day to day safety inspection on site belongs to the construction stage.

Inspections of finished or existing buildings

Not every inspection happens during a build. A buyer's solicitor may want an Opinion on Compliance for an extension that has no certificate, a buyer may commission a pre-purchase survey, and an owner will walk a finished house with a snag list. These look at what is there now, and they can only report on what can be seen or opened up.

Which inspections your job gets

Health and safety inspections by the PSCS and the HSA apply on every site. What changes with the job is who inspects the building work, and the record it leaves.

Find your inspections

What is the job?
Your jobWho inspectsWhat you are left with
Internal alterationNo inspection is required by law. The engineer who designed the beam can inspect it before it is covered.The calculations, and an Opinion on Compliance if a buyer's solicitor asks for one.
Extension of 45 m² or lessNo statutory inspection plan. The inspections are the ones you appoint.The calculations and an Opinion on Compliance.
Inside BCARWe act as assigned certifierThe assigned certifier's inspection plan, with each designer inspecting their own work at its stages. The council may also inspect.A Certificate of Compliance on Completion, and the inspection plan as carried out, lodged on the BCMS.
Opted outNo assigned certifier and no plan. The council may still inspect, and engineer's inspections before work is covered are still worth having.No completion certificate. An Opinion on Compliance when the house is sold.

When do inspections happen on an Irish build?

At the stages where work is about to be covered up. The Code's own inspection plan template for a dwelling sets them out in order, and a typical house or extension follows it closely:

  1. Excavation and formation. Is the ground at the bottom of the trench what the design assumed? Width and depth of the trench, steps in level. This is where the site investigation is proved right or wrong.
  2. Foundations. General arrangement, depth and width of concrete, and the reinforcing steel, checked before the pour.
  3. Substructure and ground floor. Rising walls, damp proof course, hardcore, radon membrane and sump, and services under the floor, before the slab goes down.
  4. Drainage. Pipe runs, falls and testing, before the trenches are backfilled.
  5. Superstructure, before the ceilings are slabbed. Walls, floors, beams and lintels, roof trusses, bracing and tie downs, insulation.
  6. Completion. Fire detection, chimneys and flues, carbon monoxide detection, ventilation, roof covering, external finishes, and the test and commissioning certificates.

Larger or more complex buildings add stages, such as a basement and its tanking, a steel or precast frame, or fire stopping. The worked example in the Code, a detached four bed house on a high radon site, comes to five inspections in total. That is an example, not a rule: the number is set by the plan for each job.

The assigned certifier agrees an Inspection Notification Framework with the owner and builder before work starts, which says which stages the builder has to call in. The Code also makes clear that certifiers may inspect unannounced between those stages.

What is checked on a site inspection?

The Code asks the inspection plan to prioritise five things:

  • elements whose failure would be significant, which on most jobs means the structure
  • unusual designs or methods of construction
  • work relating to fire safety
  • anything that, if not verified, could cause a defect seriously detrimental to the purpose of the regulations
  • whatever else is needed to sign the completion certificate

On a structural inspection that translates into concrete things: bearing ground, dimensions, bar sizes, spacing and cover, laps, steel connections, bearing lengths, propping, and whether what is on site matches the current revision of the drawing. Where a test is the better evidence, such as concrete cubes, a drainage test or an air tightness test, the plan says so in advance.

How often is a construction site inspected?

There is no single figure, because there is no single inspection.

  • Under BCAR, the Code requires a written inspection plan of "appropriate intensity and frequency", set by the risk of the job: the type of building, how complicated the construction is, the builder's experience, how serious a failure would be, whether the work can be seen again once closed up, and the speed of the build. It is reviewed as the job proceeds.
  • For safety, the Construction Regulations 2013 require every part of an excavation where people work to be inspected by a competent person every day, and thoroughly examined at least every 7 days or after anything that may have affected its stability, recorded on HSA Approved Form AF 3. Scaffold inspections are recorded on the HSA's GA3 report.
  • The building control authority decides for itself, by risk and at random.

What happens if an inspection finds a problem?

It is written down, the builder puts it right, and the person who found it checks again. The Code requires records that show what was inspected, what was found, what remedial action was needed and when it was done. Where the defect has already been covered, it is opened up at the point that matters.

Inspect the work at its stage
Does it match the design and the regulations?

Yes

Record itThe job moves on to the next stage

No

Record the defect
The builder puts it right
Inspect again

Round again until it matches

never put right
No completion certificateThe building cannot be used, and the council can enforce
What an inspection does with what it finds.

If it is not put right, the consequences escalate. The assigned certifier cannot sign the Certificate of Compliance on Completion, and the building cannot be opened, used or occupied until that certificate is validated and on the register. The building control authority can serve enforcement notices and prosecute. On the safety side, HSA inspectors can issue improvement directions, improvement notices, and prohibition notices that stop an activity immediately.

What records does a site inspection leave?

Under BCAR, the inspection reports and photographs of each certifier, the ancillary certificates, and the inspection plan as implemented, which is lodged on the BCMS with the Certificate of Compliance on Completion. On the safety side, the statutory forms kept on site, and the safety file the PSDP prepares and hands to the client at the end. Keep all of it with the deeds. It is the first thing asked for when the house is sold.

What if the work is outside BCAR?

Statutory certification applies to new dwellings, extensions over 45 m² (the threshold since 27 July 2026) and works that need a fire safety certificate. An owner of a single dwelling or a domestic extension can opt out of certification, and smaller extensions are outside it altogether.

Neither changes the duty to build to the Building Regulations. It changes the evidence. There is no inspection plan and no certificate, so whatever inspections happen are the ones the owner chooses to pay for. Having the engineer who designed the foundations and frame inspect them before they are covered costs little against a buyer's surveyor asking, years later, what is under the floor. Where the work is already finished, an Opinion on Compliance is how that question is answered at sale.

Where this office comes in

We act as assigned certifier and as design certifier, inspect and sign the ancillary certificates for the structure and the civil works we design, give Opinions on Compliance for work that has no certificate, and act as PSDP. If you have been asked for a certifier or an inspection and are not sure which one, send us the request as it was worded to you, and we will tell you what it means and who should be doing it. The phases of a construction project shows where each of these fits in the wider job.

Sources (8)
Written by
PETRUF Consulting Engineers
Published
Updated

What people ask after reading this.