PSDP and Design Risk Management

appointments, preliminary safety and health plans and safety files, under the Construction Regulations 2013.

Most building projects need a : any project with more than one contractor, a particular risk, or a build of more than 30 working days or 500 person days. The client appoints one in writing before design work starts.

The coordinates the designers so that what they draw can be built and maintained safely: hazards identified and designed out where they can be, and what remains written down for the contractor who has to deal with it.

We act as , and as designers we carry the same duties on every job: a design risk assessment with the drawings, and the information the and the need. Temporary works, where much of the construction risk sits, are designed in the same office.

What the role covers

Coordinating the designers

The architect, the engineers and the specialists designing with each other's risks in mind, and directed in writing where they are not.

Hazard identification

Hazards from the design, the programme or the site, eliminated where possible and reduced where not.

Preliminary safety and health plan

Written before tender on any project over 500 person days or 30 working days, or with a particular risk, and given to the client.

Design risk register

The risks each designer leaves behind, with the control measures, carried into the plan.

Handover to the PSCS

The design assumptions and remaining risks passed to the before construction starts.

Safety file

The record of the finished building that the next person to work on it will need, prepared and given to the client.

Who does what

The Construction Regulations 2013 split safety and health on a project between these roles. One firm can hold more than one of them, but each is appointed in writing.

Do you need a PSDP?

Will construction take more than 30 working days, or more than 500 person days?
RoleAppointedMain duties
ClientThe person or company the work is forAppoints competent designers, contractors, a and a , and on larger projects notifies the of the 's appointment.
PSDPWe act in this roleIn writing, before design work startsCoordinates the designers, prepares the preliminary safety and health plan, and prepares the safety file.
DesignersWe act in this roleAnyone preparing drawings, specifications or calculationsIdentify the hazards in their design, remove or reduce them, and pass what remains to the .
PSCSIn writing, before construction startsDevelops the safety and health plan, coordinates the contractors on site, and on larger projects notifies the before work starts.

What you receive

Each is a document the next person on the project can use.

  • The preliminary safety and health plan, ready for tender
  • A design risk register kept as the design develops
  • Coordination of the designers, with written directions where they are needed
  • The design information handed to the
  • The safety file, compiled and given to the client at completion

Send us the project.

Drawings, a specification, or the site address and the programme dates: whatever you have is enough to start. We come back inside two working days, and a written fee proposal against a defined scope follows within three working days of that.