Uisce Éireann Connections

Connections run as your agent, from the pre connection enquiry to handover, with diversions and build over agreements.

Every development that connects to the public water or wastewater network goes through Uisce Éireann, the body that was Irish Water. It is a sequence of applications, each with a wait, and the waits add up to the better part of a year before anyone is connected.

We run it as the client's agent: the pre connection enquiry, the design submission, the connection application and agreement, the diversion of any Uisce Éireann pipe that crosses the site, and the build over or build near agreement where a building comes close to one.

On site we attend the quality checks and pressure tests, produce the as built drawings, and close out the defects period until the network is handed over. The water and wastewater design itself is part of the drainage design.

What we handle

Pre connection enquiry

The first application, at the start of the design, which returns a Confirmation of Feasibility for the planning application.

Design submission

Layouts to the Uisce Éireann Code of Practice and standard details, for its Statement of Design Acceptance.

Connection application and agreement

The application after planning, the connection offer, and the agreement it becomes.

Diversions

Moving an Uisce Éireann main or sewer that crosses the site, from the application to the as built record.

Build over and build near

Agreements and method statements where a building comes within the separation distance of a public pipe.

Site quality checks

Attendance at Uisce Éireann's inspections and pressure tests, and non conformances closed out through construction.

As built drawings

The record drawings and test results the handover needs.

Defects and handover

The defects period closed out, the completion certificate obtained and the security released.

The process, and how long it takes

The averages are Uisce Éireann's own. The stages run one after another, so the first application is worth making as early as the design allows.

Plan your connection

Connected around

About 56 weeks in

Enter the date the pre connection enquiry goes in to see the dates.

Make the connection application on week 28.

  1. Pre connection enquiry to Confirmation of Feasibilityweek 0 to week 16, 16 weeks
    Uisce Éireann average
  2. Planning permissionweek 16 to week 28, 12 weeks
    Your programme
  3. Connection application to connection offerweek 28 to week 44, 16 weeks
    Uisce Éireann average
  4. Constructionweek 28 to week 54, 26 weeks
    Your programme
  5. Road opening licence to connectionweek 44 to week 56, 12 weeks
    Uisce Éireann average
  6. Defects periodweek 56 to week 108, 52 weeks
    Uisce Éireann, from the conformance certificate

Uisce Éireann's averages, not its promises: any stage can run longer. The design acceptance happens alongside the enquiry, before the planning application, and the connection needs the offer accepted, the network built and inspected, and the road opening licence in place.

StageWhat happensTypical wait
Pre connection enquiryUisce Éireann checks there is capacity and returns a Confirmation of Feasibility, which goes in with the planning applicationAbout 16 weeks on average.
Design acceptanceThe water and wastewater layout is checked against the Code of Practice and a Statement of Design Acceptance issuedBefore the planning application is finalised.
Connection applicationAfter permission, the application is made and Uisce Éireann issues a connection offerAbout 16 weeks on average.
Connection agreementThe offer is accepted and becomes the agreement, setting out the quality checks, upgrades and chargesOn acceptance.
ConstructionThe developer builds the network, Uisce Éireann's field engineers inspect it, and the mains are pressure testedWith the build.
ConnectionUisce Éireann obtains the road opening licence and makes the connectionAbout 12 weeks from the licence.
HandoverA conformance certificate starts a 12 month defects period, then final checks, a completion certificate and the security released12 months or more.

What you receive

One office between the client and Uisce Éireann, from the first enquiry to the last certificate.

  • Every application prepared and submitted as your agent, and the correspondence handled
  • Layouts to the Code of Practice and standard details in force for the application
  • Diversion and build over applications, with the method statements and surveys they need
  • Attendance at site quality checks and pressure tests
  • As built drawings and the records the handover needs
  • The defects period closed out and the network handed over

From our projects

Send us the project.

Drawings, a specification, or the site address and the programme dates: whatever you have is enough to start. We come back inside two working days, and a written fee proposal against a defined scope follows within three working days of that.