What Is BIM? Meaning, Levels, Dimensions, ISO 19650

BIM is how a project's information is created, shared and kept, not a software package. Its meaning, levels, dimensions, ISO 19650 and the Irish mandate.

Building Information Modelling (BIM) is the use of a shared digital representation of a built asset to support design, construction and operation, and to give a reliable basis for decisions. That is how ISO 19650 defines it. In practice it means a structured, coordinated model and its data that the whole team works from.

What does BIM stand for?

BIM stands for Building Information Modelling, spelt "modeling" in American English. The word that matters is information. A BIM model is not just a picture of a building. Each element knows what it is, what it is made of, where it sits and how it relates to what it touches.

"Building" is wider than it sounds: ISO 19650 says "built asset", which covers bridges, roads and water infrastructure as well as buildings. Some read the M as management, and the standard backs them, since it is titled as information management using building information modelling.

Is BIM software?

No. BIM is a process, and software supports it. Revit, Allplan, Tekla, ArchiCAD and similar packages are tools for authoring models. Owning one does not mean a project is doing BIM. The UK BIM Framework guidance makes the point bluntly: a client who simply asks for "a BIM project" will not meet the requirements of ISO 19650, and a shared drive is not a common data environment.

What is the difference between BIM and CAD?

CAD (computer aided design) draws lines, arcs and text: a digital drawing board. A wall in CAD is two parallel lines, and a section through it is drawn again by hand. In BIM the wall is an object with a type, a thickness, a material and a fire rating. Plans, sections, schedules and quantities are all views of that one object, so a change made once appears everywhere. On its own, CAD is Level 0 or Level 1 on the maturity ladder below.

What is BIM used for?

  • Design coordination. Each discipline models its own work and the models are combined, or federated, so that the structure, the services and the architecture can be checked against each other.
  • Clash detection. Software tests the federated model for elements that occupy the same space or leave no room to be installed. Every clash resolved on screen is one not resolved on site with a core drill.
  • Quantities and cost. Volumes, weights and counts come out of the model, so a bill of quantities agrees with the drawings because both came from the same source.
  • Fabrication. Shop drawings, bar bending schedules and machine files for production can be generated straight from the model.
  • Programme. Linking elements to the construction programme shows the build sequence before anyone is on site.
  • Handover and operation. The information the owner needs to run the building is delivered in a structured form instead of a box of manuals.

Our own BIM work covers all six. The structural model carries the elements, the reinforcement, the connections and the services that pass through them. We federate it with the other disciplines' models for clash checks, take bills of quantities, reinforced concrete drawings, bar bending schedules and CNC production files for precast elements out of it, link it to the programme, and hand over the asset information the owner needs to run the building. How that plays out on a precast job is in BIM implementation in precast concrete.

What are the BIM levels?

The BIM levels describe how mature a team's information management is, from paper to a fully shared model. They come from the UK, where the 2011 Government Construction Strategy set Level 2 as the target for centrally procured projects by 2016.

  1. Level 0Unmanaged CAD2D drawings on paper or file, with no common standards.
  2. Level 1Managed CADModels kept within each team, with some shared naming.
  3. Level 2CollaborativeNow ISO 19650Discipline models federated and checked in a common data environment.
  4. Level 3IntegratedOne shared online model across the asset's life, still more aim than practice.
The BIM maturity ladder. What used to be Level 2 is now BIM according to the ISO 19650 series.
  • Level 0 is unmanaged CAD. The drawings are 2D, exchanged on paper or as files, with no common standards or processes.
  • Level 1 is managed CAD. Teams may model in 3D for themselves, with some standard naming and a shared space for files, but models are not shared between the team. It is sometimes called lonely BIM.
  • Level 2 is collaborative. Each discipline builds its own 3D model with data attached. The models are exchanged in agreed formats, federated and checked together, under shared standards and a common data environment.
  • Level 3 is a single integrated, online model shared by the whole team across the asset's life. It is still more of an aim than everyday practice.

How does ISO 19650 relate to BIM Level 2?

ISO 19650 parts 1 and 2 grew out of the British standards BS 1192 and PAS 1192-2, which defined Level 2. The ISO dropped the numbering. What used to be called Level 2 is now "BIM according to the ISO 19650 series", which the UK guidance also calls Stage 2. It is mostly Level 2 with some elements of Level 1 and Level 3. In 2019 the UK replaced "BIM Level 2" with the UK BIM Framework, built on ISO 19650. The guidance adds a warning: there is no legal definition of "BIM according to ISO 19650", so a contract that only asks for it, without saying what information is needed, is asking for very little.

What is ISO 19650?

ISO 19650 is the international standard series for managing information over the whole life of a built asset using BIM. Ireland adopted it as I.S. EN ISO 19650 through the National Standards Authority of Ireland (NSAI). It has six parts:

  • Part 1: concepts and principles (2018).
  • Part 2: the delivery phase, meaning design and construction (2018).
  • Part 3: the operational phase, once the asset is in use (2020).
  • Part 4: information exchange (2022).
  • Part 5: security-minded information management (2020).
  • Part 6: health and safety information (2025).

In 2021 NSAI published an Irish National Annex to Part 2, NA:2021 to I.S. EN ISO 19650-2:2018, which sets out how to apply Part 2 on Irish projects, including the naming of files and other information containers. Parts 1 to 3 are under revision at ISO, with a new edition expected around 2027, but the 2018 editions are the ones in force.

What do the ISO 19650 terms mean?

  • Information model: the structured and unstructured information on a project, from models and drawings to schedules and documents.
  • PIM, project information model: the information developed during design and construction, which grows from the design model into the virtual construction model.
  • AIM, asset information model: the information needed to operate and maintain the asset. Relevant information passes from the AIM into the PIM when a project starts, and back to the AIM at handover.
  • CDE, common data environment: the agreed single source of information for the project or asset, where each file is collected, managed and shared through a controlled workflow.
  • OIR, organisational information requirements: what the client's organisation needs to know to meet its own objectives.
  • PIR, project information requirements: what the client needs to know about the purpose, design and construction of the asset.
  • AIR, asset information requirements: what the client needs to operate and maintain the asset.
  • EIR, exchange information requirements: what one appointment must deliver, when, in what form and to what level of detail.
  • BEP, BIM execution plan: the delivery team's answer to the EIR, saying how it will manage and deliver the information. A pre-appointment BEP is submitted with a tender, and is confirmed once the team is appointed.

Who does what on a BIM project?

Appointing partyUsually the client, who sets the information requirements and accepts the information.
requirements down, information up
Lead appointed partyThe design lead or the main contractor, who answers the requirements with a BIM execution plan.
requirements down, information up
Task teamsThe structural engineer, the services designer and subcontractors, who produce the information.
every file through
Common data environmentThe one agreed source, where every file is shared through a controlled workflow.
Who does what under ISO 19650: requirements go down, information comes back up through the common data environment.
  • The appointing party leads the project or manages the asset, and is usually the client. It sets the information requirements and receives the information.
  • A lead appointed party coordinates information between its own task teams and the appointing party. The architect leading a design team or the main contractor are typical examples, and a project can have more than one.
  • Appointed parties are anyone producing information about the project: consultants, subcontractors and suppliers.
  • Task teams are the people doing one specific job, for example the structural design team or the subcontractor designing the curtain walling.

Requirements flow down from the appointing party. Each lead appointed party answers them with its BEP and passes the relevant parts on to its task teams. Information flows back up through the CDE, checked at each step, until it is accepted by the client. Older PAS 1192 material calls the same roles employer and supplier.

What are the BIM dimensions: 3D, 4D, 5D, 6D and 7D?

The dimensions are shorthand for the kinds of information a model carries beyond its geometry.

  1. 3DGeometryThe model of the asset, with information on every object.
  2. 4DTimeElements linked to the programme to show the build sequence.
  3. 5DCostQuantities from the model linked to rates.
  4. Above 5D, sources disagree

    1. 6DSustainabilityEnergy, embodied carbon and life cycle assessment.
    2. 7DFacilities managementWhat the owner needs to run and maintain the asset.
The BIM dimensions, each one a kind of information added to the model. Above 5D, sources disagree.
  • 3D: the geometric model of the asset, with information attached to each object.
  • 4D: time. The model is linked to the construction programme to show the build sequence.
  • 5D: cost. Quantities from the model are linked to rates for estimating and cost control.
  • 6D: usually sustainability, such as energy performance, embodied carbon and life cycle assessment.
  • 7D: usually facilities management, meaning the operation and maintenance information the owner needs after handover.

Be careful with 6D and 7D. There is no agreed definition beyond 5D. Most software vendors and training providers use the order above, but NBS and Designing Buildings put facilities management at 6D and sustainability at 7D. NBS points out that the dimensions are not used in the international standards at all, and that it is better to state exactly which information is required. ISO 19650 does that through the AIR and the EIR. If a brief asks for "6D BIM", ask what it means by it.

Is BIM mandatory in Ireland?

On public works, yes, and the threshold is falling in stages. The government set out its BIM strategy in November 2017. The adoption timeline under the Capital Works Management Framework (CWMF) phases BIM in by project value, with design teams first and contractors and the supply chain six months later:

Project valueDesign teamsContractors and supply chain
Over €100m1 January 20241 January 2025
Over €20m1 January 20251 July 2025
Over €10m1 July 20251 January 2026
Over €5m1 July 20261 January 2027
Over €1m1 January 20271 July 2027
Under €1m1 July 20271 January 2028

The requirement applies to projects that begin CWMF Stage 1 on or after each date, not to projects already under way, and the timeline is subject to review. Where BIM is required, the CWMF names four core standards: the ISO 19650 series, Uniclass for classification, IFC as the open file format, and the International Cost Management Standard (ICMS) for costs and carbon. Private clients are not bound by the mandate, but many now ask for the same thing.

Where can I learn more about BIM in Ireland?

  • NSAI sells the I.S. EN ISO 19650 parts and the Irish National Annex, and offers third-party certification to ISO 19650-2.
  • The National BIM Council, with the Construction IT Alliance (CitA) as its secretariat, published Ireland's first digital strategy for construction, the Roadmap to Digital Transition, in December 2017.
  • Build Digital, funded by the Department of Public Expenditure and Reform and led by TU Dublin with CitA and other universities, produces guidance, templates and supports for meeting the BIM mandate in line with ISO 19650.

What are the benefits of BIM?

  • Fewer surprises on site. Clashes and missing information are found in the model, when they cost a revision rather than a variation.
  • One version of the truth. Drawings and schedules cannot fall out of step, because they are views of the same model held in one CDE.
  • Better prices. Tenders can be checked against measured quantities instead of estimates.
  • A useful handover. The owner gets structured asset information instead of a pile of PDFs, which is where a digital twin begins.

The benefits depend on the client stating what it needs. A model built without requirements is only an expensive drawing. With clear requirements, BIM does what it promises: the right information, to the right people, at the right time.

Sources (12)
Written by
PETRUF Consulting Engineers
Published
Updated

What people ask after reading this.